Site visit — issues discovered
Notes:
- Cracks observed in all rooms
- Multiple doors not closing
- Backyard fire suppression water tank access door not closed
- Window open; water intrusion with visible watermarks
Punch list submitted to contractor
Notes:
- Comprehensive punch list sent via email covering ADU and main house items
- 11 specific items identified for immediate fixes and checks
- Requested downspout extension, drywall crack repairs, electric panel access finishing
- Door alignment, floor level checks, entry step verification requested
- Main house stucco repair and downspout repair requested
- Construction material removal and extra water tank removal requested
Related Issues:
Wall cracks in multiple rooms Doors not closing (frame shift) Electric panel access needs finishing Downspout extension needed Floor level verification Entry step code compliance Window security verification Main house stucco repair Main house downspout repair Extra water tank on site Construction materials and amenities removal
Contractor response received
Notes:
- Doors confirmed complete - no additional work needed
- Floor level checked in bedroom - verified good
- All windows confirmed locked
- Interior cracks will be repaired after power is on
- Electric panel access to be finished by GC
- Entry step confirmed code compliant; pricing additional step and railing
- Downspouts not extended by contractor - homeowner to provide extenders
- All materials and cleanup to be done before final walkthrough
- Waiting for PG&E to schedule power connection
Follow-up confirmation request
Notes:
- Requested confirmation on extra water tank removal
- Requested confirmation on full removal of garden amenities per original agreement
- Awaiting final walkthrough after utilities connected and punch list complete
Related Issues:
Contractor final confirmation
Notes:
- Confirmed all materials and tank will be removed during final cleanup
- Cleanup to occur after all touch-ups and before final walkthrough
- Still waiting for power connection from PG&E